This quick reference guide describes the correct installation of the Bauder Bitumen Parapet Outlet DN 100.

It is essential that you read these instructions before installing the Bauder Parapet Outlet DN 100 and refer to the project specification for the location of this outlet.

Important

⚠️ Warning
Bauder has taken care to ensure that the literature is correct and up to date. However, it is not intended to form any part of a guarantee. Contact Bauder to check whether there has been any changes to this literature. Please ensure you have read the recycling instructions and dispose of all packaging responsibly.

Components

The Bauder Parapet Outlet DN100 with pre-assembled pipe can be cut to suit the parapet’s requirements.

Dome grate to prevent leaf litter etc entering the pipe.

Page 1_1

General Advice

With the installation of any flat roof rainwater drainage outlets BS EN 12056-3:2000 should be observed.

Some points to observe are:

  • The rainwater outlet should be installed at the low point of the roof falls.
  • The outlet is an integral component of the Bauder waterproofing system and this precaution is important to prevent damage to the outlet and the waterproof connecting flange prior to installation.
  • The outlet body must be mechanically fixed to the wall.
  • Roof outlets must be freely accessible for maintenance.

Installing to Cold / Inverted Roofs

1

Push the Bauder Parapet Outlet together with the pre-attached connection pipe through the core drill into the parapet.

Page2_1

2

Mechanically fix the flange of the outlet body to the wall.

Page2_2

3

Apply the waterproof layers, bonding the underlayer on to the bituminous connection flange provided.

Page2_3

4

Insert the dome grate and tighten as necessary to ensure a tight fit.

Page2_4