BauderJFRI Inverted Insulation Installation Guide

This guide describes the correct installation of BauderJFRI PREMIUM inverted insulations for podiums and flat roofs where the construction is designed with an inverted roof and specified with a Bauder waterproofing system.

Page2_1

Prerequisites

  1. This guide MUST be read in conjunction with the specification to confirm the products used and layout of the scheme.
  2. The installation MUST NOT commence until the information within this guide is understood.

Conditions

The Bauder guarantee may not be issued if:

  1. The waterproofing fails to meet inspection standards.
  2. Any component is incorrectly installed.

Disclaimer

For any damage caused by improper use, faulty planning, installation by operatives without sufficient training, or use for unintended purposes, no warranty product guarantee or liability is accepted by the manufacturer.

Standards & regulations

Our products are manufactured in accordance with applicable standards and technical regulations and therefore correspond to all relevant technical standards.

For the use of this product, all locally applicable standards, current legal requirements, building regulations, and applicable accident prevention regulations must be observed.

Technical Support

If you require support or advice on Bauder Inverted Insulations, or products within the specification please contact:

  • Andrew Harper
    Hot Melt Product Manager
    +44 (0)7469 853264
  • Technical Department
    +44 (0)1473 257671
    [email protected]
⚠️ Warning
IMPORTANT

Waterproofing precondition

The roof deck must be level and even (see BS6229:2018) and as dry as is practically possible. Ensuring a dry deck reduces the risk of high levels of condensation once the insulation and waterproofing is installed.

For Bauder Bakor 790-11 Hot Melt System:

■ Conduct Peel Test to PASS standard.
■ Install two 3mm layers of Bauder Bakor 790-11 with Bauder Polyester Reinforcement between the layers.
■ Bauder AP1 Access Sheet fully bonded into Bauder Bakor 790-11 second layer. Use minimal Bakor 790-11 to fully bond laps. Any excess material scraped and discarded to leave a clean, smooth finish.

1.1 Inspecting the insulation boards prior to installation

  1. Carry out initial visual checks for thickness and rebate irregularities.
  2. If required, follow visual with physical thickness and rebate checks.

    Quarantine any boards that do not conform and notify your Bauder Site Technician.

    Quarantined boards could be used as cuts/infills providing the thickness is not the reason they are quarantined.

Page 3_1

1.2 Prior to installing the insulation boards

  1. Inspect the completed waterproofing to ensure it is clean, free of debris and suitable to receive insulation.
  2. Do not start installation until other sub-trades are free of the roof.
  3. The specification may call for warm or inverted upstands. Ascertain which and install accordingly prior to the installation of the horizontal inverted insulation to the main area.
⚠️ Warning
Insulation stated within the specification

Confirm in the specification if the insulation is to be installed as a single or multi-layer solution.

1.3 Installing the insulation boards to the main area

  1. Commence from the chosen wall allowing for safe access of materials and operatives whilst maintaining debris free waterproofing surface. Choose a starting point that will reduce the amount of foot traffic on installed insulation.
  2. Use a laser or physical line to ascertain any irregularities of the chosen wall/installed upstand insulation.
  3. Lay the first line of insulation in a straight line from chosen wall/installed upstand insulation. This may require cutting boards into an irregular upstand to achieve the correct starting off point for the remainder of the roof.
  4. Where cutting boards is not required but minor gaps occur between upstand wall and horizontal insulation use a Miothene Compressible Strip to close any gaps.
  5. Lay the Bauder Inverted Insulation in brick bond pattern, rebated edges pushed firmly together.
  6. Boards should be laid with the Jablite logo on the upper side and in the same rotational plane.
  7. If two layers of insulation are employed the top layer must be offset from the bottom layer.

Bond-on-bond between layers will not be accepted.

  1. Ensure there is no springing or flexing of the boards. This is an ongoing process until the entire installation is completed.
  2. Minimise foot traffic on completed work prior to ballast installation. Use scaffold boards/ply etc when barrowing materials over the insulation/WFRL.
  3. Fit/cut Bauder Inverted Insulation boards neatly around penetrations. Gaps to be filled using Expandable Foam.
⚠️ Warning
Planning the installation sequence

Carefully set out to minimise cutting the boards and where possible avoid using pieces less than 150mm wide.

1.4 Passivhaus process - where applicable

  1. Checks to be undertaken by Roofing Contractor and designated Main Contractor Passivhaus Inspector or Passivhaus Inspector if on site.
  2. Checks to be photographed/videoed and report sent to Passivhaus Inspector for Sign Off. This procedure could be carried out by Passivhaus Inspector if on site. If installation is made up of two or more insulation layers, confirmation of what needs to be photographed/videoed must be sought from Passivhaus Inspector prior to work commencing.
  3. Inspection process should not interfere with the correct installation procedures for products involved.

1.5 Installing the Bauder Water Flow Reducing Layer (WFRL)

  1. Loose lay the BauderJFRI WFRL with 300mm laps at right angles, horizontally across the fall, to the slope.
  2. On zero-falls roofs, use the same principle based on the outlet positions.
  3. At upstands and penetrations turn up the BauderJFRI WFRL so that it finishes above the ballast. For drainage outlets it is turned down to cover exposed insulation.

1.6 Installing the ballast

  1. Use scaffold boards/ply etc when barrowing materials over the insulation and WFRL.
  2. Lay the ballast progressively to secure the insulation boards.
  3. Work on an advancing front from the point of access so all ballast material is carried across a protected waterproof layer.
  4. Take care on distributing ballast evenly across the roof area during installation.
⚠️ Warning
IMPORTANT

Ballast MUST be installed immediately to secure the insulation boards against wind uplift, fire risk or flotation.

1.7 Installation of associated elements