BauderSOLAR G LIGHT Biosolar Mounting System Installation Guide
Introduction and Prerequisites
This guide describes the correct installation of the BauderSOLAR G LIGHT biosolar mounting system for Bauder green roofs.
Prerequisites
- This guide must be read in conjunction with the Bauder specification to confirm the products used, installation method, and specific project array layout and dimensioned roof layout.
- Understanding of all sections is mandatory.
- Operatives carrying out installation of the BauderSOLAR G LIGHT system MUST be competent and trained in the specific system installation method.
- Workmanship MUST comply with Bauder Ltd installation guidance.
Conditions
The Bauder guarantee may not be issued if:
- There is no safe access to inspect the roof area(s).
- The installation fails to meet final inspection standards.
- Any specific component is substituted for an equivalent without the written authority of Bauder Ltd.
⚠️ Warning
The information within this guide ONLY relates to the installation of the BauderSOLAR G LIGHT components and does NOT provide any guidance on solar photovoltaic (PV) electrical requirements such as inverter specification or electrical connectivity to the building. It is the responsibility of the electrical contractor to adhere to relevant electrical standards and best practice.
Further information on electrical best practice can be found on the MCS website.
https://mcscertified.com
The Bauder PV array layout observes the standards and guidelines from:
BS EN 1991-1-4 Wind Actions on Structures
BRE Digest DG489 rev 2014
Confirmation should be sought from the correct authority if using associated standards pertaining to the installation of a solar PV array.
Technical support
If you require support or advice on the BauderSOLAR G LIGHT System or products within the specification, please contact:
- Bauder Technical Department +44 (0)1473 257671
- [email protected]