Inspections
5.1 Regular inspections
Regular inspections are to be carried out to determine obvious damage and impairments.
Refer to specific maintenance guides for waterproofing system and PV array available on our website www.bauder.co.uk/technical-centre/installation-maintenance.
5.2 Electrical equipment
These must be carried out by a qualified electrician to all electrical plant components which are operated in combination with the BauderSOLAR flat roof system, in particular for the sake of preventive fire protection, as per DIN VDE 0105-100 and DIN VDE 0126-23, at intervals of four years maximum.
5.3 Photovoltaic modules
Allowance should be made for annual cleaning of the solar modules.
Please see module manufacturer’s guidelines for further information.