Operation and Maintenance
4.1 Safe operation
The BauderSOLAR flat roof system has an operating life of 20 to 25 years, assuming proper planning, installation, commissioning and maintenance, as specified in this manual.
It is recommended to maintain permanent operational data monitoring with fault detection of the electrical components.
4.2 Maintenance and cleaning
In order to maintain the continued safe operation of the BauderSOLAR system, the following should be carried out during the planned period of use:
- Annual visual and strength tests
- Regular inspections of electrical safety
- Annual inspections of the roof waterproofing
- Regular cleaning operations
⚠️ Warning
Follow the guidance for operation and maintenance of all ancillary components
To ensure safe operation, maintenance, and cleaning, observe the manufacturer’s instructions, warnings, and installation conditions for installed connection components (photovoltaic modules, cable support systems, solar cables, power optimisers, etc).
For all electrical elements which are operated with the BauderSOLAR flat roof system, successful commissioning tests should be provided according to MCS requirements.
To ensure safe operation, maintenance, and cleaning, observe the manufacturer’s instructions, warnings, and installation conditions for installed connection components (photovoltaic modules, cable support systems, solar cables, power optimisers, etc).
For all electrical elements which are operated with the BauderSOLAR flat roof system, successful commissioning tests should be provided according to MCS requirements.