Drainage and Water Storage Products

3.1 SDF L drainage layer

SDF L drainage layer nylon loop mesh sandwiched between two sheets of geotextile fleece providing drainage, protection and filtration layer for an extensive green roof.

Technical data
Thickness20 mm
Size (w x l)1 m x 50 m
Coverage50 m²
Weight0.6 kg/m²

⚠️ Warning
Cutting: Use a flat blade and a protection board (see Section 1.4).

Placeholder image

General installation

Placeholder image

  • Unroll SDF L mat to cover entire area across the roof. It can be laid either way up, and butt-jointed. (see Photo A)
  • Unfold the geotextile flaps and lay over the adjacent mat.
  • Cut SDF L mat tightly around all upstands and penetrations.
  • Cut oversized hole above each outlet and ensure they remain clear.
  • SDF L mat should be installed at 90˚ to the direction in which the XF 301 will be laid. (see Photo B)

Placeholder image

Installation with BauderGREEN AL 40 edge trim

  • Check AL 40 is fitted correctly (see Section 7.2).
  • SDF mat should be set back by 50 mm from the face of the AL 40. The XF 301 sedum blanket is tucked under the AL 40 to hold the edge down.

Placeholder image

Installation with vegetation barrier

Where 20-40 mm pebble ballast is used to weigh down the XF 301 the SDF L mat should be cut just short and pebbles installed according to the specification.

Tips:

  • SDF L mat will try to curl up during installation.
  • 25 kg bags of pebbles or substrate can be used to weigh down ends.

Placeholder image

3.2 DSE 20/1 water storage layer

High-density polyethylene combined water storage and drainage layer.

Technical data
Thickness20 mm
Size (w x l)1.06 m x 2.36 m
Weight1.2 kg/m² dry; 8.6 kg/m² water-filled
Water storage7.4 Ltr/m²

⚠️ Warning
Cutting: Use a flat bladed knife and protection board (see Section 1.4).

placeholder

Installation

  • Normally installed over a protection layer.
  • Lay each sheet (open cells up) over the entire area so they overlap by one full cell.
  • Stagger the joints, brick pattern.
  • Cut a hole in the drainage board over the outlet slightly smaller than the inspection chamber that is being placed above it (see Section 7).

placeholder

Installation with drainage trim

  • Check drainage trim is installed correctly prior to fitting DSE 20/1 (see Section 7).
  • DSE 20/1 should be cut to about the edge of the drainage trim.
  • Avoid any cross joints by offsetting the membranes.

placeholder

Installation with vegetation barrier

Where possible, DSE 20/1 should run under the entire area of the green roof from upstand to upstand, including below the vegetation barrier.

placeholder

Tips:

  • DSE 20/1 should not be fitted in gutters.
  • Filling the DSE 20/1 with water will help hold the sheets in place.
  • Where a number of sheets of DSE 20/1 come together at one point, overlapping every cell on the sheets edge may not be possible.

3.3 DSE 40 water storage layer

High-density polyethylene combined water storage and drainage layer.

Technical data
Thickness40 mm
Size (w x l)1.04 m x 2.03 m
Weight1.8 kg/m² dry
Water storage13.5 Ltr/m²

⚠️ Warning
Cutting: Use a handsaw or hacksaw and a protection board (see Section 1.4).

placeholder

Installation

  • Normally installed over a protection layer.
  • Lay each sheet (open cells up) over entire area so they overlap by one full cell, as marked by 'X' on each sheet.
  • Stagger the joints, brick pattern.
  • Cut a hole in the drainage board above the outlet, slightly larger than the inspection chamber.
  • Fit the drainage board around the inspection chamber (see Section 7.1).

placeholder

Note:

Details of the RE 40 attenuation and drainage board utilised in blue roofs is covered in the Blue Roof Components Installation guide (Section 10.2).

placeholder

Installation with drainage trim

  • Install and inspect drainage trim (see Section 7) prior to fitting DSE 40.
  • DSE 40 should be cut to about the edge of the drainage trim.

placeholder

Installation with vegetation barrier

DSE 40 should run under the entire area of the green roof from upstand to upstand, including below the vegetation barrier.

Installation with hard landscaping

Where hard landscaping features such as paving and brick work are to be formed, install concrete and subbase materials directly into the cells of the DSE 40.

Tips:

  • DSE 40 should not be fitted in gutters.
  • Filling the DSE 40 with water will help hold the sheets in place.
  • Where a number of sheets of DSE 40 come together at one point, overlapping every cup on the sheet's edge is not possible.

placeholder

3.4 DSE 60 water storage layer

High-density polyethylene combined water storage and drainage layer for intensive green roofs. DSE 60 is able to withstand vehicle traffic.

Technical data
Thickness60 mm
Size (w x l)1 m x 2 m
Weight2 kg/m² dry
Water storage with mineral drain fill10-12 Ltr/m²

⚠️ Warning
Cutting: Use a handsaw and protection board (see Section 1.4).

Installation

  • Normally installed over a protection layer.
  • Lay each sheet (drainage holes uppermost on the crowns) over entire area, butt together and overlap the edge lips.
  • Stagger the joints, brick pattern.
  • Cut a hole in the drainage board above the outlet, slightly larger than the inspection chamber that is being fitted (see Section 7.1).

Installation with pebble barrier

DSE 60 should run under the entire area of the green roof from upstand to upstand, including below the pebble barrier.

Installation with mineral drain, concrete foundation or subbase

  • Fill the cells of the DSE 60 board with mineral drain level with the top surface of the crowns after settlement.
  • Where used with Type 1 subbase, DSE 60 should be over-filled and then mechanically compacted.
  • Where hard landscaping foundations are to be formed in concrete, install concrete directly into the cups of the DSE 60.

Tips:

  • DSE 60 should not be fitted in gutters.
  • Filling the DSE 60 with water will help hold the sheets in place.

3.5 WSP 50 or 75 water storage layer

Expanded polystyrene combined water storage and drainage board for flat or pitched green roofs.

Technical dataWSP 50WSP 75
Thickness50 mm75 mm
Size (w x l)0.8 m x 1.3 m1 m x 2 m
Weight0.65 kg/m² unfilled0.95 kg/m² unfilled
Water storage10 Ltr/m² when flat21.5 Ltr/m² when flat

⚠️ Warning
Cutting: Use a handsaw and protection board (see Section 1.4).

3.5.3

General installation for flat roofs 0-5°

  • Lay out boards with open cells uppermost, interlocking the rebated edges.
  • Stagger the boards tightly, brick pattern.
  • Cut boards accurately around upstands and details.
  • Cut a hole in the WSP larger than the outlet and slightly smaller than the inspection chamber that is being placed above it (see Section 7.1).

3.5.4

3.5.5

Between 5-15° pitched roof installation

  • Lay the boards out horizontally to the slope of the roof.
  • Start at the bottom kerb or batten.
  • Lay FV 125 filter fleece if detailed in the specification (see Section 4.1).
  • Fill each board with either water or substrate as soon as it is fitted.

3.5.6

Greater than 15° pitched roof installation

  • Follow instructions as above, filling each board to the crowns.
  • Loose lay untreated wooden trellis (approx 150 x 150 mm squares) over entire roof area.
  • Complete substrate installation to required depth, as detailed in specification.

3.5.7

Tips:

  • Boards are extremely light so filling installed boards with water will help to prevent wind uplift.
  • Keep trafficking of the boards to a minimum as they can be easily damaged. Use crawler board where required.