Vegetation
Manual Sections
6.1 XF 301 sedum blanket
Pre-cultivated sedum vegetation blanket with integral geotextile filter fleece and 8-mm moisture retention layer attached to the underside.
| Technical data | |
|---|---|
| Supply form | 1 m x 2 m rolls (15 rolls/pallet) Long rolls up to 10 m |
| Thickness | 28 mm |
| Weight | 44 kg/m² saturated |

Manual Handling: 2-m rolls of XF 301 are too heavy to be handled by one person.
Cutting: Use a sharp knife or angle grinder and a protection board to prevent damage to the waterproofing (see Section 1.4).
General installation
- Installation sequence must begin at the far end of the roof so the XF 301 is not walked on.
- Clean sedum and substrate from side and end lap to give a straight edge and enable a butt joint with no visible gaps.
- Any sedum and substrate removed from joints should be saved for patching.
- Lay sedum rolls on top of previous lap, in a staggered brick pattern, only full or half rolls around perimeter. Always cut on a protection board.
- Thoroughly water areas of XF 301 as they are installed.
- On completion of the day's installation, fill open joints or bare areas with salvaged sedum and substrate, utilising any unused mats and further substrate as an additional source, before watering in (see Section 8.1).

Installation with BauderGREEN SDF L
- If SDF L mat is specified, finish the mat 100 mm short of the vertical face of the AL 40.
- Trim blanket to length required and tuck under the AL 40 lip to secure the end and prevent wind uplift.
- XF 301 will be laid at 90˚ to the SDF L mat laps.

Installation with pebble barrier
Extend blanket 100 mm beneath the pebbles to anchor the blanket against wind uplift.

Pitched Roofs
- Retention strips should be installed prior to the XF 301 sedum blankets. Normally greater than 10˚ for bitumen membrane waterproofing and greater than 5˚ for single ply (see Section 7.5).
- XF 301 should be installed on long rolls, via a crane, on barrel-shaped and steep-pitched roofs.

Aftercare
Water the XF 301 sedum blanket to establish the vegetation (see Section 8.1).
Tips:
- On completion, take photos of roof to record condition.
- Record that aftercare advice has been given to main contractor regarding watering, trafficking and storage on the roof.

6.2 SB and WB vegetation blankets
Pre-cultivated vegetation mats grown on 100% biodegradable coir carrier installed on top of Bauder substrate.
| Technical data | SB | WB |
|---|---|---|
| Supply form | 0.5 x 2 m rolls; approx 35 rolls/pallet | 0.5 x 2 m rolls; approx 35 rolls/pallet |
| Thickness | 25 mm | 30 mm |
| Weight | ≤ 24 kg/m² saturated | ≤ 28 kg/m² saturated |

Manual handling: SB or WB blankets are too heavy to be handled by one person.
Cutting: Use a sharp knife or angle grinder and a protection board to prevent damage to the waterproofing (see Section 1.4).

General installation
- Ensure substrate and any required drainage trim is fitted prior to installing SB or WB blankets.
- Start at the far end of the roof to prevent walking on the vegetation.
- Clean off loose vegetation and substrate from the edge of the blanket to give a straight edge. Save these for patching.
- Lay SB/WB blanket tight-butted, in a staggered brick pattern, only full or half rolls around perimeter.
- Thoroughly water areas of vegetation mats as they are completed.
- On completion of the day's installation, fill open joints or bare areas with salvaged vegetation and substrate, utilising any unused mats and further substrate as an additional source, before watering in (see Section 8.1).

Installation with drainage trim KFL AL 100/80 or AL 150
- Ensure that filter fleece FV 125 is dressed up the inside of the drainage trim and held in place by substrate.
- Install vegetation mats so that top of the blanket is finished level with the top of the trim.
- Trim blanket to required length.
- Only install lengths of over 500 mm adjacent to the edge of the system.

Installation with vegetation barrier
- Where vegetation mat is laid with pebble vegetation barrier, the blanket should stop along the line of the FV 125 separation sheet.
- Ensure vegetation mat and pebbles are level (i.e. at the same height).


Installation to pitched roofs
Avoid trafficking of the finished system as it will cause the substrate to slip down the roof.
Aftercare
Water the blankets to establish the vegetation (see Section 8.1).
Tips:
- On completion, take photos of roof to record condition.
- Record that aftercare advice has been given to main contractors regarding watering, trafficking and storage on the roof.
6.3 BauderGREEN Plugs
Pre-grown plants grown in plug format for individual planting on a substrate-based green roof.
| Technical data | |
|---|---|
| Supply form | 4-cm plugs - 104 per tray 5-6-cm plugs - 54 per tray Native species plugs - 104 per tray |
| Pallet | 60 trays per pallet |
| Planting rate | As per project specification |
| Weight | ≈ 5 kg/tray |

Installation
- Plug planting should be the last construction activity on the roof and should take place in the spring or autumn months.
- Do not plant the plugs if there is no means to water them during establishment.
- Ensure the substrate is at the correct level and use a spazzle to give a smooth finish.
- Begin at the far end of the roof so the vegetation is not walked upon.
- Work 10-m² area at a time, lay out the plugs in a random pattern with no more than 3-4 species per m² and do not position any within 100 mm of the edge.
- Ensure plant density is as per specification.
- Make a hole in the substrate, place plug into hole so that the soil in the plug is level with the substrate.
- Firm up substrate around the plug.
- Thoroughly water each 10-m² area as soon as completed, using a soft spray.
- Continue with the next 10 m².
- Do not traffic or disturb the planted area, as growth of the plants will be affected.
Storage:
Inspect the plants on delivery, checking for damage and quality. Keep moist and water regularly to prevent plugs drying out. Plugs will survive for 4-5 days if they are kept moist and out of direct sun.
Planting:
Use a dibber or trowel to plant. Only plant 10-m² areas at a time. Best establishment will be achieved in spring and autumn.
Aftercare
Follow instructions in Section 8.1.
Tips:
- On completion, take photos of roof to record condition.
- Record that aftercare advice has been given to main contractor regarding watering, trafficking and storage on the roof.
- Roofs may require netting to prevent birds from pulling up the plug plants.
- Do not plant if there is a risk of frost.
6.4 Flora seed mixes 3, 5, 7, 9 & 11
A balanced mix of British native seed and growing material, including organic nutrients and mycorrhizas to assist with installation and establishment process.

| Technical data | Value |
|---|---|
| Supply form | 2 kg, 5 kg and 20 kg bags |
| Sow rate | 100 g/m² |
| Coverage | 2 kg = 20 m², 5 kg = 50 m², 20 kg = 200 m² |
Storage:
Store in dry conditions for a maximum of 1 year. If the seed mix becomes damp prior to installation, it must be discarded.
Seeding:
Ideally sow in spring or autumn. Do not seed in midsummer unless there is adequate watering. Avoid sowing in strong winds or frosty conditions.
Installation
- Ensure the SUB-SBS UK substrate is at the correct level and use a spazzle to give a smooth finish.
- Water the substrate thoroughly prior to spreading the seed mix.
- Seed in two passes at 90˚ to each other.
- DO NOT water or rake afterwards.
- DO NOT traffic or disturb the seeded area as this will affect germination of the seed.
Aftercare
Follow instructions in Section 8.1.
6.5 Vegetation barrier
20-40-mm washed, rounded pebbles used as a fire break around the perimeter of the green roof and at upstands, rooflights and penetrations.
XF 301 does not always require a vegetation barrier to act as a fire break. Check the project specification to confirm its inclusion.
| Technical data | |
|---|---|
| Supply form | As per supplier specification. Typically 25-kg bags or bulk bags |
| Coverage | Typically 50 kg required per 1 m x 500 mm of border |

Do not land the bags directly onto the vegetation blanket.
Installation
- Ensure correct protection layer is installed prior.
- Ensure leaf guards or inspection chambers are fitted to outlets before arranging pebbles around them.
- Spread pebbles evenly to a depth of 75 mm, or as per specification.
- Discard any sharp pebbles that may cause damage.
- Distribute pebbles to overlap the XF 301 by 100 mm thereby providing anchorage.
- Use a scaffold plank to give pebbles a straight line on top of the XF 301.
Tips:
- Pebbles can be ramped up or down to meet the top edge of vegetation trim.
- Although bulk bags can be more cost-effective, moving the pebbles around the roof will be much slower.