Separation and Protection Layers
Manual Sections
2.1 PE 02 separation layer
Polyethylene foil plastic sheet which acts as a separation/slip layer between the waterproofing and the green roof build-up and is generally used on intensive roofs or under hard landscape up to 3°.
| Technical data | |
|---|---|
| Thickness | Ca. 0.2 mm |
| Weight | 190 g/m²; 50 x 4 m, folded on 1-m roll |
| Coverage | 200 m² (in a single layer) |
⚠️ Warning
Cutting: Use a flat blade or scissors and a protection board (refer to Section 1.4).

Installation
- Unroll and unfold PE 02 into a single layer.
- Overlap by minimum 150 mm at all joints.
- Lay out to cover entire roof area.
- Mark the location of outlets and ensure the PE 02 is removed from these positions to maintain drainage.
- Extend beyond the finished surface level at all upstands. Trim later as required upon completion of the landscaping.
Extensive green roofs:
- If required, PE 02 must be cut well back from drainage outlets and inspection chambers.
Intensive green roofs:
- If two layers are required beneath soft landscaping, lay at 90° to each other.

2.2 FSM 600 & FSM 1100 protection layers
Heavy duty protection layer made from polyester and polypropylene fibres.
| Technical data | FSM 600 | FSM 1100 |
|---|---|---|
| Thickness | 4 mm | 8 mm |
| Size (w x l) | 2 m x 30 m | 2 m x 15 m |
| Coverage | 60 m² | 30 m² |
| Weight | 600 g/m² | 1100 g/m² |
⚠️ Warning
Cutting: Use a sharp knife or scissors and a protection board (see Section 1.4).
Hot works: Bauder no longer recommends the torching together of FSM layers.
Hot works: Bauder no longer recommends the torching together of FSM layers.

Installation
- Lay out protection layer under all green roof finishes, including pebble borders, etc.
- Roll out over the roof space, allowing a 150 mm overlap at joints.
- Use metal foil tape tape to hold down the fleece, or 25-kg bags of pebble to counter wind uplift.
- Can be dressed up perimeter upstands by 100 mm (or to the top of the landscape finish).
- Should be cut well back from outlets.

Extensive green roofs:
- Do not extend FSM protection mat up the perforated face of drainage trims.
- Cut oversized hole above each outlet.
- Check outlets are clear of protection mat.
- On completion of the vegetation installation, trim the FSM protection mat level with the vegetation barrier. Use a cutting board against upstands etc. to cut against.


2.3 SV 600 protection layer
Lightweight protection layer made from recycled man-made fibres that also provides some water retention.
| Technical data | |
|---|---|
| Thickness | 6 mm |
| Size (w x l) | 2 m x 30 m |
| Coverage | 60 m² |
| Weight | 0.6 kg/m² dry; 3.8 kg/m² saturated |
⚠️ Warning
Cutting: Use a flat blade or scissors and a protection board (see Section 1.4).

Installation
- Lay out to cover entire roof area. Overlaps to be a minimum of 150 mm or as determined in the specification.
- Extend beyond the finished surface level at all abutment upstands. This will later be trimmed as required upon completion of the landscaping.
Extensive green roofs:
- Do not extend SV 600 up the perforated face of drainage trims.
- Cut oversized hole above each outlet.
- Check outlets are clear of SV 600.
- On completion of the vegetation installation, trim the SV 600 level with the vegetation barrier. Use a cutting board against upstands etc. to cut against.
Note:
- SV 600 can be used as a moisture retention layer under XF 301 sedum blanket in dry areas such as ridge lines on pitched roofs.


2.4 GGM 6 protection layer
Heavy-duty protection layer for intensive green roofs made from recycled rubber.
| Technical data | |
|---|---|
| Thickness | 6 mm |
| Size (w x l) | 1.25 m x 10 m |
| Coverage | 12.5 m² |
| Weight | 4.3 kg/m² dry |
⚠️ Warning
Cutting: Use a flat blade and a protection board (see Section 1.4).
Compatibility: GGM 6 is not compatible with Thermofol PVC single ply and MUST NOT be laid directly onto this membrane. It is compatible with Thermoplan FPO.
Compatibility: GGM 6 is not compatible with Thermofol PVC single ply and MUST NOT be laid directly onto this membrane. It is compatible with Thermoplan FPO.
Installation
- Lay out to cover entire roof area.
- Overlaps to be a minimum of 150 mm or as determined in the specification.
- Carefully cut GGM 6 so it fits the full surface area of the roof. For intensive green roofs, do not extend GGM 6 up the perforated face of drainage trims.
- Cut oversized hole above each outlet. If green roof installation is not imminent, loose laps can be taped together to eliminate the trip hazard.
- Check outlets are clear of GGM 6.